Winam-IP-Kids Playground
Description:
As chinese saying goes preparedness ensures success. If you have the time schedule about kids playground, you can prepare everyting to catch the opening of your playground accordingly.
- Product Details
- Specifications
- Image
The delivery time of kids playground around 300sqm
Some clients have exact time to open their kids playground, so they have to make detailed schedule about the delivery time. And we believe other clients have this question if they place the order, it will take how long to get their goods. Here we list a time schedule of playground around 300sqm, the time is from the date we confirm the final design.so you can exactly know how you should do at each step..
No. | Assignment | Time | Person chiefly in charge | Remaks |
1 | confirm design and quotation | Dec 29th-30th 2018 | WINAM/Client | |
2 | sign contract | Jan 2nd | WINAM/Client | |
3 | site measurement | Jan 2nd | WINAM/Client | we confirm all measure with you before placing production order. |
4 | pay deposit | Jan 3rd | Client | |
5 | start production after receiving deposit | Jan 3rd | Cowboy | urgent order can start production after seeing the deposit bill |
6 | finish production | Jan 24thWINAM | we can do the visa for engineers at the same time | |
7 | goods inspection and prepare for loading | Jan 24th | WINAM/Client | receive balance before loading |
8 | receive the balance | Jan 24th | WINAM | |
9 | loading container | Jan 25th | WINAM | |
10 | customs clearance | Jan 25th | WINAM/Client | we provide documents |
11 | shippment | Jan 26th | WINAM/Client | |
12 | ETA and customs clearance | Feb 10th | Client | The shipping time depends on where is your arrival port |
13 | install team arrive | Feb 13th | WINAM/Client | we send 2 engineers, you hire 2 workers to assist.Take about 15 days to finish |
14 | finish installation | Feb 29th | WINAM/Client | |
15 | clean the site | Feb 30th | Client | |
16 | opening ceremony | Mar 1st | Client |